Project details

CPMM (Citic Pacific Mining Management Pty Ltd) on behalf of Sino Iron Pty Ltd (Sino Iron Project)

Cargo collection point

Daebul, South Korea
Cargo delivery point

Cape Preston, Western Australia
Category

Mining
DESCRIPTION

NMT co-ordinated the shipping and Project management logistics of approximately 32,000 freight tons of A-frame dolphins, marine piles & steelwork from Daebul port, South Korea to the Cape Preston mine site and discharged the cargo at the service jetty in
Cape Preston W.A.

The cargo will be shipped over two shipments over a period of one month, with the heaviest piece being approximately 61t, and pieces being over 30m long, up to 10m wide and 9m high.

NMT facilitated the movement of the cargo from under the ships hook in Daebul to its delivery at the mine site, including Loading and Discharge operations, Shipping, Customs & Quarantine Clearance into Cape Preston, W.A.